We are pleased to announce that we completed a Billet Welding Machine fast-track revamping project in Germany.
We performed the civil works during a shutdown period of 13 calendar days (from December, 27th 2019 to January, 09th 2020) and we delivered the new foundations 5 days before the contractual date.